Pipe Clamping Mattresses
Step-change in arresting pipeline walking
Developed by Subcon in cooperation with Shell Global Solutions (Shell), the engineered 'pipe clamping mattress' (PCM) is used to mitigate pipeline-walking.
With rock-dumping the vast majority of load is passed straight to the seabed, but with PCMs 100% of the load is effective in mobilizing axial resistance.
The technique was first developed on Shell's Malampaya Project; as an alternative to traditional rock dumping. Shell presented a technical paper on the Malampaya PCM’s at the Houston OTC available here
Specification Title | Specification Description |
---|---|
Accuracy
|
Clamping tolerance ~1mm (client issued pipeline to make the mould).
|
Areas of Application
|
Pipeline Walking Mitigation or Rectification.
|
Installation
|
PCMs can be installed as a pair (with the log mat) thus halving the installation time.
|
Lifespan
|
50 years
|
Material
|
Fibre reinforced concrete with neoprene lining.
|
Modular design
|
PCMs are deployed in banks determined by total restraining capacity.
|
Patents
|
Shell has a US patent pending for the PCM, but has now released the PCM option to the market via a global licensing agreement with Subcon.
|
Response time
|
PCMs can be designed, fabricated and installed in circa 4 months (thereby suitable for a wait-and-see approached where pipeline walking is reacted to).
|
Reviews
Sign up or log in to your explorer or platform subscription to get access to the reviews written about this technology.
The Technology Readiness Level (TRL) indicates the maturity level of novel technologies. Learn more about the TRL scale used by us.
[9/9]
Relative Business Impact
Sign up or log in to your explorer or higher plan to get access to all the 1 deployment references.
Last Deployment YearTotal DeploymentsComment